As part of the investment “Works on Railway Line No. 131 on the Chorzów Batory – Nakło Śląskie Section”, DYSTEN will deliver over 140 passenger information devices to the stations in Chorzów, Bytom and Radzionków.
The equipment will include:
- collective station displays,
- edge platform displays,
- single-sided multi-function displays,
- double-sided multi-function displays,
- entrance platform displays,
- train presence sensors.
DYSTEN will integrate the devices with the Central Dynamic Passenger Information System CSDIP PKP PLK.
The modernization is part of the project “Works on the C-E 65 Railway Line on the Section Chorzów Batory – Tarnowskie Góry – Karsznice – Inowrocław – Bydgoszcz – Maksymilianowo” co-financed by the EU Operational Programme Infrastructure and Environment.
All works are scheduled to be completed in 2025.